


Dear Lara, My technician, Steven, went to the site and changed out the charge controller main board. The problem was caused more
Attendance: Cheku local community, Women and Men Venue: Cheku more
THE 2 WATER CONCRETE TANKS REPORT. The work of building 2 concrete tanks finished on 1st April 2011, now more
Hi Lara, Loc and Zoe... I am just update, I met Mary even though today here is holiday most of more
The pump test was completed and the pump yield as specified. We had a problem with a faulty float switch more
Dear Lara, This is to inform you that the pump is installed and pumping. The pump test was completed and the more
Thanks Lara, the work is very hard and everything going great!! The concrete water tanks today going to be more
Dear Lara, My technicians are on site. As stated, the installation will be done on time. Unfortunately the customs issues did not more
Hello Lara, Loc and Zao.... On 21 we left Kondoa Town at 09:00am, on this day we used hired jeep again, more
The work of building 2 concrete tanks finished on 1st April 2011, now the Cheku water project had this long more
The test for the Cheku borehole were conducted on October 24th, 2009 and it has been determined that the water more
The process of digging the borehole took over 9 months but we finally dug a hole that, once we install more
